Friday 18 August 2017

bricks continuing (week 14)

So the workers have been busy all week on the bricks and will need next week to continue.

Asked the supervisor for an update on the timeline and this is what he has advised:

We are still working away with the brickwork. I would say the guys need all of next week to complete at this stage. Possibly a little longer. 

I have scheduled the job out after that including eaves installation, brick cleaning, downpipes, window cleaning, painting and scaffold removal. Ive also then scheduled in lower fascia and guttering, safety railing, roof install, lower eave, lower acid clean, lower downpipes and then the electrical wiring internally as well as air con install. 

By that stage, we will be ready for the certifier to inspect the framework before we can progress onto the gyprock. 


Enjoy your weekend. 

Thursday 10 August 2017

finally workers onsite! (week 13)

After no workers for 6 days we finally had some action. Our superivisor has said they will be there till all the bricks are done. Lets hope we will get to lock up stage soon.


Tuesday 1 August 2017

More bricks (week 12)

So this week the scaffolding got lowered so that the upper bricks can be done. More bricks also got delivered. That was the first two days and then nothing was done the rest of the week.


Benchtops, basins and painting (week 26)

There has been a lot happening in the house the past two weeks, The painting has continued, the wet area tiing is complete, all architraves ...