Tuesday 24 October 2017

Wet area tiling (week 24)

The wet tile area got prepared and the tiles have been laid. The wet area wall tiles as well as the balcony have been tiled. Now waiting for grouting etc to be done.

The kitchen cabinets are still not all up due to some error. Hopefully it will get fixed up soon.

Abbey blinds and Shutters are coming to measure our windows next week so they can start manufacturing our roller blinds.





Cabinets and tiling (week 24)

Drove past the house on Monday morning to see a Fab kitchens truck in the driveway delivering our kitchen and bathroom cabinets.

Very happy with how the cabinets came out. The colour is Polar White in natural finish.


Kitchen counter against the wall - still needs more cabinets and a rangehood


                                                            Island cabinet in kitchen


Inside kitchen cabinet - double bins in cupboard

Island kitchen cabinet with 60cm cutlery draws


Laundry cabinet by the window with mineralstone laminex counter.


Laundry side counter. Left side is for the tumble dryer and thinking about wire shelves to keep washing in or otherwise laundry baskets.

Butlers pantry leading to laundry



Butlers pantry


Kitchen

Bathroom cabinet in Silver Riftwood Laminex - love the colour (photo does not show true colour)

                                                                        Linen cupboards







Saturday 21 October 2017

Stairs, doors, waterproofing and architraves (week 23)

Well this was a busy week at the house with all types of activities happening.

Firstly, the stairs got put in and are looking great





We also had the waterproofing done in all the wet areas.

powder room

laundry

laundry

bedroom 2 ensuite

balcony

main ensuote

main ensuite


All the doors were put in and the architraves.


front door put in


Media room door on and working on architraves and doors earlier in the week


Tuesday 10 October 2017

Cornices and hopefully stairs (week 22)

This week the cornices have been put in and now hopefully the stairs will come later this week.

It was very interesting to see on the camera the way the cornices get placed (see below)







Friday 6 October 2017

We have walls! (week 21)

We were away this week enjoying a nice break in Port Stephens. It was still nice to logon to Build watch and see the work being done.

The walls got insulated and gyprocked this week.





Benchtops, basins and painting (week 26)

There has been a lot happening in the house the past two weeks, The painting has continued, the wet area tiing is complete, all architraves ...