Some scaffolding was removed after the windows and upper downpipes got painted. Some bricks on the lower level got cleaned (except for where the scaffolding has remained).
The garage has been cleaned and cleared for the lower roof to commence.
Plans for the rest of this week is lower roof, lower eaves and balcony sheeting and frame straightening.
Showing posts with label scaffolding. Show all posts
Showing posts with label scaffolding. Show all posts
Wednesday, 20 September 2017
Tuesday, 1 August 2017
More bricks (week 12)
So this week the scaffolding got lowered so that the upper bricks can be done. More bricks also got delivered. That was the first two days and then nothing was done the rest of the week.
Tuesday, 25 July 2017
Roof tiles (week 11)
Well so far this week has been buzzing with lots of activity on our property. Monday was lots of delivery for scaffolding and Tuesday it got assembled for the roof to be completed and tiled. Wednesday there was a big team that completed the roof and the tiles (except for the garage).
It really looks like a house now.
It really looks like a house now.
photo from the Build watch cam - nothing wrong with the added view!
Subscribe to:
Posts (Atom)
Benchtops, basins and painting (week 26)
There has been a lot happening in the house the past two weeks, The painting has continued, the wet area tiing is complete, all architraves ...
-
I went to Homeworld Kellyville to see Metricon as I loved the Liberty and the Franklin. The Liberty could not fit on my property but the Fra...
-
There has been a lot happening in the house the past two weeks, The painting has continued, the wet area tiing is complete, all architraves ...
-
Well this was a busy week at the house with all types of activities happening. Firstly, the stairs got put in and are looking great ...