Friday, 18 August 2017

bricks continuing (week 14)

So the workers have been busy all week on the bricks and will need next week to continue.

Asked the supervisor for an update on the timeline and this is what he has advised:

We are still working away with the brickwork. I would say the guys need all of next week to complete at this stage. Possibly a little longer. 

I have scheduled the job out after that including eaves installation, brick cleaning, downpipes, window cleaning, painting and scaffold removal. Ive also then scheduled in lower fascia and guttering, safety railing, roof install, lower eave, lower acid clean, lower downpipes and then the electrical wiring internally as well as air con install. 

By that stage, we will be ready for the certifier to inspect the framework before we can progress onto the gyprock. 


Enjoy your weekend. 