Monday 19 June 2017

Frames continuing (week 5 & 6)

Last week was not very productive due to heavy rain and very wet conditions. A bit of work got done later in the week and even on Saturday. Today they worked hard and started the alfresco and garage frame as well as putting in some windows.













Tuesday 6 June 2017

Frames (week 4)

Well today it really feels like we are building a house!!

Went past the house at 8:30 to see nothing but a slab and then at 3:45pm the ground floor frames are up.

We could start working out where the rooms are etc and it is so exciting.

Rain is predicted for the rest of the week but hopefully only at night.












Friday 2 June 2017

Drainage (week 4)

Now that the slab is complete and is curing - this week involved plumbing work. Drainage, sewerage , power etc was worked on.

Some of the frames got delivered this week.














Benchtops, basins and painting (week 26)

There has been a lot happening in the house the past two weeks, The painting has continued, the wet area tiing is complete, all architraves ...