Lower bricks cleaned & painting (week 18 and 19)

Some scaffolding was removed after the windows and upper downpipes got painted. Some bricks on the lower level got cleaned (except for where the scaffolding has remained).

The garage has been cleaned and cleared for the lower roof to commence.

Plans for the rest of this week is lower roof, lower eaves and balcony sheeting and frame straightening.

Tuesday, 5 September 2017

Brick cleaning, eaves and downpipes (week 17)

So now that the bricks are complete they are getting cleaned. Top floor bricks have been cleaned.

The top floor has started. Today the eaves got put in and some downpipes.




Benchtops, basins and painting (week 26)